Articulos 2008

December 2008 Update

Monday, December 1, 2008

The golf driving range at Paraiso del Mar is officially open on the weekends from here on out! We had a wonderful sneak preview event at the golf driving range December 6th and 7th for over 200 people of La Paz via invitation. The event was a wonderful success. Attendees received impromptu golf lessons, were provided golf clubs and were allowed to hit unlimited balls. Plenty of refreshments were on hand.

Paraiso's temporary grocery store is almost complete, the temporary club house and palapa is under construction and the tennis courts are in progress. The Arrival Palapa is even more comfortable and inviting everyday.

The palm trees and landscaping are starting to go in at the A Building and first condominium horseshoe.

Owners who have moved into the single family neighborhood are meeting their neighbors, enjoying the pool and secluded beaches and raving about the Paraiso staff and service. Some are even sneaking in a round of golf on the soon to be opened course at Paraiso del Mar.

Actualización General Fotos Aereas

Sabado, Septiembre 20, 2008

A continuacion le mostramos fotografias aereas de la propiedas que fueron tomadas el 20 de Septiembre del 2008.

Actualización Campo de Golf

Jueves, Septiembre 4, 2008

El campo de golf  de Paraíso del Mar esta ya casi terminado y realmente toda la gente ya empieza a hablar de nuestro campo de golf

 

Al  4 de Septiembre del 2008 hemos terminado por completo los hoyos 1, 2, 3, 4, 9, 16, 17, 18, el campo de práctica y el área de tiro corto. Además, la constructora O&J ya sembró el pasto en los hoyos  5, 6, 7, 8, 11, 12, 13 y 15 desde los tees hasta los green. Anticipamos terminar el sistema de riego en los dos hoyos que quedan pendientes (10 y 14), que son par 3`s para inicios de la próxima semana y empezar a sembrar el pasto en los 10 últimos greens inmediatamente después.

 

Con la llegada de las lluvias las plantas del desierto han florecido y complementan la belleza del lugar. Justin Maddox y su equipo de mantenimiento del campo de golf también le dan la bienvenida a las lluvias recientes y están realizando un extraordinario trabajo tratando de mantener el crecimiento del verde pasto paspalum.

 

Hemos sido muy afortunados de tener esta maravillosa oportunidad de trabajar con Stuart Bruening de Universal Golf Development y el equipo administrativo de Paraíso del Mar en la creación del primer campo de golf de campeonato de 18 hoyos en  La Paz y estamos muy complacidos por la respuesta de aquellos que han visitado las instalaciones. Si todo marcha como lo planeamos, esperamos que el campo de golf esté listo para jugar a finales de año.

 

Brian Yoder, ASGCA

Principal

Arthur Hills/Steve Forrest and Associates

 

Progreso General

Martes, Agosto 12, 2008

Paraíso del Mar tiene el honor de informar que los primeros propietarios de casas ya se mudaron a sus casas. Felicidades a nuestros primeros residentes. Para finales del mes se entregaran 30 llaves a dueños de Paraíso del Mar.

Paraíso tiene una nueva oficina que funciona como recepción en Vista Coral. Esta recepción tiene una ambiente agradable, mesas y sombrillas en el exterior para disfrutar las vistas ubicada en el muelle privado de Paraíso.

La Marina Vista Coral esta al final del malecón a la izquierda del Hotel Los Arcos viendo hacia Paraíso. Hay muy buenos restaurantes en esta área  de Vista Coral para desayunar, comer o cenar, lo cual es muy conveniente para nuestros residentes.

Ambos muelles están operando y tenemos transportación y seguridad (24/7) así como la recepción. Una gran palapa esta en construcción en el muelle de Paraíso del Mar.

Un gran progreso se ha realizado en el exterior de los condominios. Recientemente los barandales de herrería se han instalado en los condominios. La alberca esta casi terminada y una vez que este lista tendremos servicio de comida rápida y bebidas.

El campo de golf esta quedando muy bonito, adquiriendo un color más verde cada día. John Fair ya golpeo su primera bola en Paraíso.

Back View of Building A Las Casas Neighbourhood Building A Building B Terrace Area Building A Casa Luna Model Casa Playa Model Condos View from Malecon Driving Range

Actualización General

Miercoles, Junio 18, 2008

La jardinería esta casi terminada en 25 casas. El crecimiento del pasto en los hoyos 16, 17, y 18 va progresando y los próximos seis hoyos ya han sido sembrados. La construcción de los greens inicia a finales del mes. Se finalizo con el dragado del área del muelle de Recepción/Partida en la Ciudad así como en la Propiedad. El edifico A esta substancialmente terminado, las ventanas están siendo instaladas en el edificio B con el trabajo de acabados interiores empezando en el 6to piso. Los edificios del C al J continúan progresando en los exteriores con algo de acabados interiores también iniciando.

Progreso General

Viernes, Mayo 16, 2008

La jardinería inicia en las próximas 25 casas. Los hoyos 16, 17 y 18 ya han sido sembrados con seis hoyos mas iniciando a finales del mes. Se ha iniciado con la pintura exterior del edificio B así como las estructuras de los techos han sido terminadas en los Edificios C, D, E y F.  El emplastado del interior en el Edificio B da inicio y el progreso se extiende a la segunda herradura.

A view of Golf Holes 16 and 17 (taken from Building S viewing Platform) Hole 18 has really taken hold.  Hole 16 starting to green up. Sod is laid on Las Casas sites Landscaping Crews prepare to start another Casa Palm Trees are planted on Beachfront homes Exterior Painting begins on Building B Progress on Building A Progress on Building B Progress on Building C Progress on Building D Progress on Building E Interior Plaster going into Building B Progress on Building F Progress on Building G Progress on Building H Progress on Building I Progress on Building J

Progreso General

Miercoles, Abril 30, 2008

¡Las Casas Modelo han sido amuebladas! El trabajo en el Muelle de Arribo ha iniciado con el dragado del área a punto de terminar. El exterior del Edificio A esta casi completo y las estructuras de los techos se terminaron en los edificios B y E. El trabajo de nuevo dio inicio en la segunda herradura.

.

Great Room Furniture in Casa Playa Model Master Bedroom Furniture in Casa Playa Model Great Room Furniture in Casa del Sol Model Master Bedroom Furniture in Casa del Sol Model Great Room Furniture in Casa de la Luna Model Building A Exterior is nearly complete Roof Structure is completed on Building B Penthouse Walls nearly completed on Building C Penthouse Walls nearly completed on Building D Roof Structure is completed on Building E Construction resumes on Building F Construction resumes on Building G Construction resumes on Building H Construction resumes on Building I Construction resumes on Building J Starfish on the shore of Paraiso del Mar

Progreso General

Martes, Abril 8, 2008

El pasto en el Campo de Golf ha tenido buen progreso. El hoyo 18 ya se esta empezando a ver verde. Las Casas Modelo ya están siendo decoradas mientras se terminan otras casas. Los Equipos de Acabados están instalando las puertas y gabinetes en los Penthouse del Edificio A y el trabajo de Emplastado continua progresando en el edifico B. La Primera Herradura esta empieza a tomar forma.

Roof work being completed on Building E Penthouse walls getting started on Building D Building A continues to move to completion Crews working on interior wall finishes in Building B Penthouse walls partially complete in Building C Roof for Building B is almost complete Another View of Building E Grass starting to take hold of 18th Fairway Grass on Short Game Practice Facility really filling in nicely Reverse Angle of Driving Range Furniture starting to be installed in Model Homes Great Room Area of Estrella Model Home Reverse Angle of Great Room Area of Estrella Model Home First Community Pool of Las Casa Neighborhood Different angle of First Community Pool for Las Casa Neighborhood

Progreso General

Miercoles, Marzo 26, 2008

 

La construcción del Campo de Golf continúa avanzando con la siembra del hoyo 18 y el crecimiento del pasto en el Campo de Práctica y el Área de Practica de Tiro Corto. Las estructuras de las Villas se perfilan a ser terminadas y permiten a los trabajadores iniciar con los trabajos en el interior. El área residencial de Las Casas continúa progresando.

 

Painting continues on Exterior of Building A Roof Structure is nearly completed on Building B Front angle of Buildings B, C, and D 5th floor walls of Building E are nearly complete Plaster is applied in Penthouse A-502 Floor tile is being installed in Penthouse A-501 Building D from Pool Area Building C from Pool Area Block of Las Casas ready for Landscaping Progress continues on more Las Casas Another Block of Las Casa progressing Another Block of Las Casa progressing More Las Casas are nearly ready for Landscaping The 18th hole is seeded (reverse angle) Short Game Practice area is taking shape and growing in Grass continues to fill in Reverse angle of Driving Range

Progreso General

Martes, Marzo 11, 2008

 

La primera capa de pintura se aplica al Edificio A.  Se están realizando trabajos en las primeras casas para tenerlas listas para el inicio de los trabajos de jardinería. La primea alberca en el área de las casas esta en construcción.

Backyard areas of First Beachfront Casas Kitchen of a Casa del Sol with Mexican Package Front yard areas of First Beachfront Casas Kitchen of a Casa del Mar with Natural Stone Package Progress is being made on Second Block of Beachfront Casas Kitchen of a Casa de la Luna with Upgraded Standard Package Progress continues on other Blocks of first 91 Las Casas First Community Pool is under way in Las Casas Driving Range is filling in Another angle on Driving Range Large Lake is completed and filled Building A is getting first coat of Exterior Paint Building B continues to move forward Beachside of Building A Beachside Building D Beachside of Building E Beachside of Building C Buildings A, B, and C

Rapido Progreso en Paraiso del Mar

Martes, Febrero 19, 2008

Continuamos presenciando grandes cambios en Paraíso del Mar. El pasto en el campo de golf ha sido plantado y la construcción de la alberca en el área de las casas esta en camino. Esta actualización ilustra el rápido progreso y trabajo que se ha realizado en tan solo dos semanas, especialmente en el área de Las Villas Condominios. En el edificio A, los equipos de trabajo se encuentran terminando los acabados, incluyendo la instalación de gabinetes y puertas interiores en el 2do piso,  la instalación del azulejo, pintura en el 4to piso y la aplicación de emplastado interior en los Penthouses. El primer piso del A esta casi terminado. Aunado a esto, el trabajo continua en el 6to piso del edifico B, C y el 4to piso del D así como 5to piso del E, mientras los trabajos de jardinería y pintura exterior continúan en el área de las casas.

 




Progreso en Areas Residenciales

Miercoles, Enero 30, 2008

Un apreciable progreso se ha realizado en la última semana y media desde nuestra ultima actualización. El trabajo de jardinería en las casas modelo muestra un gran avance y les da un acabado más lozano. En los Condominios, los equipos de trabajo continúan escalando en los edificios del B al E, así como avanzando en los interiores y techos del Edifico A. Además, la alberca para la herradura del Edificio A al E esta tomando forma conforme se levantan las paredes. En el campo de golf, las tuberías del gran lago proceden al llenado con agua del segundo lago en el campo de golf. Y el campo de practica ya esta preparado para la siembra, que dará inició muy pronto. ¡Vea estas fotos para ver nuestro progreso!

Casa Playa Kitchen 2 different types of Transportation for Paraiso del Mar Lot 59 (Beachfront Casa Playa with Casita) Backside of Beachfront Homes Casa del Mar Model Home
Progress on the Large Lake of the Golf Course Swimming Pool for Buildings A - E (Building A in background) Buildings A and B Building E (Working on 3 Floor Walls) Buildings C and B
Building B (working on 5th Floor Walls) Las Villas Swimming Pool from 4th Floor of Building B Building C (working on 3rd floor walls) Buildings D and E in foreground and G and F in Background Driving Range

Actualización del Progreso

Miercoles, Enero 16, 2008

Es sumamente emocionante ver los interiores de las primeras Casas y Condóminos. Los equipos de trabajo han progresado en los edificios A al F. En el área residencial de las Casas, los avances en la instalación de cocinas, así como la hermosa jardinería. Las calles interiores ya han sido terminadas en ambas áreas.

 

En el campo de golf, los sistemas de riego están operando. Además, la tubería para el gran lago esta casi terminada. Esperamos proveerle con más actualizaciones en el futuro cercano. Vea nuestro progreso en estas fotos.

.

Kitchen of Building A, unit 101 2nd Master Bathroom of three-bedroom condominium Pool Walls being formed on Building E (Building F in background) In Building A, interior work is being completed
Building B, 4th floor Buildings B and C Landscaping on model homes Casa de la Estrella model
Rear landscape on Luna and Estrella homes Casa Luna kitchen Casa del Sol kitchen 1st block of beachfront homes

 

Actualización del Progreso

Miercoles, Enero 9, 2008

El año Nuevo ha traído progresos en Paraíso del Mar. Ya tenemos el primer taxi eléctrico, que será utilizado para transportar a propietarios y visitantes desde el Malecón a la propiedad. Los condominios se encuentras en varias etapas de terminación y los trabajos han iniciado en la alberca para los edificios A al E. En suma, las Casas modelo han tomado una nueva apariencia conforme la jardinería va tomando forma. Vea estas fotos para que aprecie nuestro progreso.

 

Paraiso del Mar's first electric water taxi Building B (background), Building C (foreground) Roof installation and interior work underway on Building A Building of 4th floor walls on Building B Platform of first condominium swimming pool
Work on 4th floor of Building B and 2nd floor walls of Building C Layout of pool for Buildings A thru E Another look at 4th floor walls of Building B Landscaping of Casa del Sol model
Model homes with landscaping Courtyard landscape of Casa de la Estrella Progression on the some of the first 91 homes Casa de la Estrella kitchen