News Articles 2008

General Update

Wednesday, June 18, 2008

Landscaping nearly complete on first 25 homes. Holes 16, 17, and 18 are growing in nicely with the next six holes seeded. Greens to be started by end of month. Dredging is completed for Reception/Departure Dock in City and also on Property. Building A is substantially complete, windows being installed in building B with interior finish work starting to move up to 6th floor. Buildings C through J continue to progress on Exterior with some finish work starting to happen as well.

General Progress

Friday, May 16, 2008

Landscaping begins on the next 25 homes. Holes 16, 17, and 18 are now seeded with six more holes to start by the end of the month. Exterior Painting has begun on Building B as Roof Structures are completed on Buildings C, D, E, and F. Interior plaster starts on Building B and progress continues on second horseshoe.

A view of Golf Holes 16 and 17 (taken from Building S viewing Platform) Hole 18 has really taken hold.  Hole 16 starting to green up. Sod is laid on Las Casas sites Landscaping Crews prepare to start another Casa Palm Trees are planted on Beachfront homes Exterior Painting begins on Building B Progress on Building A Progress on Building B Progress on Building C Progress on Building D Progress on Building E Interior Plaster going into Building B Progress on Building F Progress on Building G Progress on Building H Progress on Building I Progress on Building J

General Progress

Wednesday, April 30, 2008

Las Casa Models are now furnished!! Work on Arrivals Dock has begun with the dredging of the area nearing completion. Exterior of Building A is nearly completed and roof structures are completed on Buildings B and E. Work has also started again on the second horseshoe and it is really taking off.

Great Room Furniture in Casa Playa Model Master Bedroom Furniture in Casa Playa Model Great Room Furniture in Casa del Sol Model Master Bedroom Furniture in Casa del Sol Model Great Room Furniture in Casa de la Luna Model Building A Exterior is nearly complete Roof Structure is completed on Building B Penthouse Walls nearly completed on Building C Penthouse Walls nearly completed on Building D Roof Structure is completed on Building E Construction resumes on Building F Construction resumes on Building G Construction resumes on Building H Construction resumes on Building I Construction resumes on Building J Starfish on the shore of Paraiso del Mar

General Progress

Tuesday, April 8, 2008

Grass on the Golf Course really taking hold. The 18th hole is already greening up and filling in. Las Casa Models starting to be decorated while other homes continue to be completed. Finish Crews are installing Cabinets and Doors in Penthouse units of Building A and Plaster work moves forward in Building B. First Horseshoe is really taking shape.

Roof work being completed on Building E Penthouse walls getting started on Building D Building A continues to move to completion Crews working on interior wall finishes in Building B Penthouse walls partially complete in Building C Roof for Building B is almost complete Another View of Building E Grass starting to take hold of 18th Fairway Grass on Short Game Practice Facility really filling in nicely Reverse Angle of Driving Range Furniture starting to be installed in Model Homes Great Room Area of Estrella Model Home Reverse Angle of Great Room Area of Estrella Model Home First Community Pool of Las Casa Neighborhood Different angle of First Community Pool for Las Casa Neighborhood

General Progress

Wednesday, March 26, 2008

Golf Course continues to move forward with the seeding of 18th fairway and continued grow-in on the Driving Range and Short Game Practice area. Las Villas structures move toward completion and allow crews to move inside to complete interiors. Las Casa neighborhoods continue to show completion.

Painting continues on Exterior of Building A Roof Structure is nearly completed on Building B Front angle of Buildings B, C, and D 5th floor walls of Building E are nearly complete Plaster is applied in Penthouse A-502 Floor tile is being installed in Penthouse A-501 Building D from Pool Area Building C from Pool Area Block of Las Casas ready for Landscaping Progress continues on more Las Casas Another Block of Las Casa progressing Another Block of Las Casa progressing More Las Casas are nearly ready for Landscaping The 18th hole is seeded (reverse angle) Short Game Practice area is taking shape and growing in Grass continues to fill in Reverse angle of Driving Range

General Update

Tuesday, March 11, 2008

Grass taking hold on Driving Range and Large Lake is completed. The first coat of paint is applied to Las Villas Building A. Final Grading being done on some of the first homes to make ready for landscaping. Las Casas first community pool is underway.

Backyard areas of First Beachfront Casas Kitchen of a Casa del Sol with Mexican Package Front yard areas of First Beachfront Casas Kitchen of a Casa del Mar with Natural Stone Package Progress is being made on Second Block of Beachfront Casas Kitchen of a Casa de la Luna with Upgraded Standard Package Progress continues on other Blocks of first 91 Las Casas First Community Pool is under way in Las Casas Driving Range is filling in Another angle on Driving Range Large Lake is completed and filled Building A is getting first coat of Exterior Paint Building B continues to move forward Beachside of Building A Beachside Building D Beachside of Building E Beachside of Building C Buildings A, B, and C

Quick Paced Progress at Paraiso del Mar

Tuesday, February 19, 2008

We continue to experience great changes on the Paraiso del Mar site. The driving range turf has planted and the single-family homes community swimming pool is underway. This update illustrates the quick pace of work over a nearly two-week period, especially in the Las Villas neighborhood. In Building A, crews are completing finish work, including cabinetry and interior door installation on the 2nd floor, tile work on the 3rd floor, painting on the 4th floor and application of interior plaster coats in the Penthouses. The first floor of A is mostly complete. In addition, work is underway on Building B’s 6th floor, C and D’s 4th floor, and E’s 5th floor. And, landscaping and exterior painting continues in the Casa neighborhood, creating a wonderful curb appeal with Mexican flair.




Neighborhood Progress

Wednesday, January 30, 2008

Obvious strides have been made in the last week and a half since our last update. Further work on Las Casas model home landscaping shows an even more lush setting. In Las Villas neighborhood, crews continue their upward climb on Buildings B through E, as well as advancing through the interior and the roofing of Building A. In addition, the swimming pool for Buildings A through E is taking shape as the construction team erects the walls. On the golf course, the lining of the large lake proceeds as we near filling this second golf course lake with water. And, the driving range has now been prepared for sprigging, which will begin soon. View these photos to see our progress!

Casa Playa Kitchen 2 different types of Transportation for Paraiso del Mar Lot 59 (Beachfront Casa Playa with Casita) Backside of Beachfront Homes Casa del Mar Model Home
Progress on the Large Lake of the Golf Course Swimming Pool for Buildings A – E (Building A in background) Buildings A and B Building E (Working on 3 Floor Walls) Buildings C and B
Building B (working on 5th Floor Walls) Las Villas Swimming Pool from 4th Floor of Building B Building C (working on 3rd floor walls) Buildings D and E in foreground and G and F in Background Driving Range

Progress Update

Wednesday, January 16, 2008

It’s exciting to see the interiors of the first Casas and Villas continuing to come together. Crews are progressing nicely on buildings A through F. In the Casa neighborhood, kitchen installation advances, as does the beautiful landscaping. Interior roads are being completed as needed throughout both neighborhoods.

On the golf course, the sprinkler system is operating. In addition, the lining of the large lake is nearly complete. We look forward to providing you with more updates in the near future. View our progress in these photos.

Kitchen of Building A, unit 101 2nd Master Bathroom of three-bedroom condominium Pool Walls being formed on Building E (Building F in background) In Building A, interior work is being completed
Building B, 4th floor Buildings B and C Landscaping on model homes Casa de la Estrella model
Rear landscape on Luna and Estrella homes Casa Luna kitchen Casa del Sol kitchen 1st block of beachfront homes

Progress Update

Wednesday, January 9, 2008

The new year has brought new progress to Paraiso del Mar. The first electric water taxi, which will be in use to transport owners and visitors from the property to the Malecon, is in our possession. The condominiums are in various stages of completion and crews have begun work on the pool for Buildings A thru E. In addition, the Casa model homes have taken on an exciting curb appeal as landscaping takes shape. View these photos to see our progress.

Paraiso del Mar’s first electric water taxi Building B (background), Building C (foreground) Roof installation and interior work underway on Building A Building of 4th floor walls on Building B Platform of first condominium swimming pool
Work on 4th floor of Building B and 2nd floor walls of Building C Layout of pool for Buildings A thru E Another look at 4th floor walls of Building B Landscaping of Casa del Sol model
Model homes with landscaping Courtyard landscape of Casa de la Estrella Progression on the some of the first 91 homes Casa de la Estrella kitchen